Save Time with BLÜCHER® EuroPipe

Postens Terminal Berger's complete roof drainage system installed in just 800 labour hours instead of 2000

BLUCHER_europipe_typemark_sq

Share this Case Study

Industry

Manufacturing & Industrial,
Other Industries

Category

Product(s) Installed:

Customer

A large storage hotel

Location

Bergen, Norway

Scope

Supply piping for an area of around 42,000 m2

What Client Needed

Long-lasting piping and roof drainage system that could be installed in roughly 1,000 labour hours.

Solution

BLÜCHER® EuroPipe

Result (ROI)

Roof drainage system with an estimated 2,500 m of pipes connected to ca 120 roof drains installed in just 800 labour hours.

Partner(s)

Bulk Eiendom AS and Aug Larsen AS (Bravida Norge AS)

Torstein Røsholt
Product Responsible
BLÜCHER Norway

“The EuroPipe-pipes are much lighter, so they can be handled by just one person. That saved us a lot of heavy lifting and made it possible for us to work more efficiently.”